Building Project: July 27 Update

July 27, 2021

Building LACMA Film Series

How will areas of LACMA’s collection come to life as never before in the new David Geffen Galleries at LACMA? Find out in a series of short videos about the new building coming to our campus.

Construction Update

The following work will be conducted this week:

  • Preparation of soils in the subgrade for foundation pile installations on the Spaulding Lot continues. Additional foundation pile testing starts next week.
  • Excavation to the top of foundation piles on the east side of the construction site, north of Wilshire Boulevard, is complete. Additional pile testing will start next week.
  • Foundation mud slab pours on the east side of the construction site, north of Wilshire Boulevard, start. Mud slab pours for the foundation will continue for several weeks.
  • Testing of foundations piles on the west side of the construction site, north of Wilshire Boulevard, will complete next week.
  • Installation of vertical waterproofing for the foundation on the west side of the construction site, north of Wilshire Boulevard, continues.
  • Preparation for foundation mud slab pours on the west side of the construction site, north of Wilshire Boulevard, continues. Pours will start next week.
  • Excavation, shoring, and tieback installations on the west side of the construction site, north of Wilshire Boulevard, continue.
  • Extraction of paleontological fossils uncovered in several sections of the construction site north of Wilshire Boulevard is ongoing and continues by paleontological consultants in accordance with the EIR and as agreed by the Natural History Museum.

Construction Hours

Monday–Friday: 7 am–7 pm

Saturday: 8 am–6 pm

Health and Safety

Our general contractor, Clark Construction, continues working diligently to provide a safe work environment for the crews working on the site, particularly during the coronavirus pandemic. To that end, and in accordance with recent adjustments made by the Cal/OSHA standards board on June 17, 2021, Clark Construction and its subcontractors have taken all necessary protective measures in accordance with government guidelines, which include the following:

  • As with all of their ongoing projects throughout the country, Clark Construction is requiring that all work be done in accordance with OSHA guidelines and industry best practices, with workers in full protective gear, including approved head, hands, and eye protective equipment, as well as safety vests and protective shoes and clothing.
  • Employees who are not fully vaccinated are required to wear face coverings while indoors and in vehicles, when accompanied by others.
  • Fully vaccinated employees, who have voluntarily provided vaccination status to their employer, do not need to wear face coverings.
  • Face coverings are not required outdoors. However, Clark and its subcontractors have communicated to workers that face coverings are recommended for persons who are not fully vaccinated when outdoors, when six feet of physical distancing cannot be maintained.
  • Clark and its subcontractors are providing face coverings to persons who are not fully vaccinated and to any persons who request them.
  • Hand washing stations continue to be maintained for workers’ use at multiple locations on site.
  • The practice of cleaning all high-touch areas, including portable bathrooms and shared tools, has continued.
  • Workers are encouraged to wash hands frequently, and anyone who exhibits any respiratory symptoms is requested to quarantine at home.
  • Clark's on-site Supervision and Safety personnel are designated and in charge of ensuring implementation of all proper protocols and guidelines.

Visit buildinglacma.org to learn more, and check out our project FAQs.